钾肥扩建时间表

 


 
2008
Mosaic Expansion Program Initiated
2008
Belle Plaine Stage 1 Expansion Project Begins
2008
Esterhazy K2 Expansion Project Begins
 
2009
Colonsay Expansion Project Begins
2009
Esterhazy K3 Expansion Receives Approval
 
2010
Esterhazy K3 Site Work Begins
 
2011
Colonsay East Wet Mill/Screening and Crushing Structural Steel Complete
2011
Esterhazy K2 Expansion Efforts Turned Over to Operations
2011
Belle Plaine Stage 1 Rotary Dryer #3 Installation
2011
Esterhazy K3 Shaft Sinking Contract Awarded. Largest Single Construction Contract Ever Awarded by Mosaic
2011
Belle Plaine Stage 2 Feasibility Study Begins
2011
Belle Plaine Compaction Expansion Receives Approval
 
2012
Expansion Program Achieved 3 Million Hours Without a Lost Time Accident
2012
Esterhazy K2 Expansion Scheduled Completion for Assembly of all Additional Mining Machines
2012
Esterhazy K3 Shaft Sinking Scheduled to Begin
2012
Belle Plaine Stage 1 Scheduled for Commissioning and Turnover to Operations
 
2013
Colonsay Expansion Project Scheduled for Completion
 
2017
Esterhazy K3 Expansion Scheduled for Production of 1.0M TPY
 
2020
Esterhazy K3 Underground Development Scheduled for Completion
 
2021
Anticipated Completion of Mosaic Expansion Program
2008  2009  2010  2011  2012  2013  2017  2020  2021